Guides · Guide
Certifying a fibre network: the complete guide.
Eight stages in working order, from the optical budget calculation to the reaction-to-fire class written into the specification. Every stage points to the note that goes deeper and to the service page that carries it out.
Certifying a fibre network is not an end-of-job activity: it is the consequence of eight decisions taken along the whole route, from the first sum of decibels to the specification line about the cable sheath. If one of those decisions is skipped, testing hands it back as an out-of-threshold event, and correcting it with the cable already buried costs an order of magnitude more.
This guide lines up the eight stages in the order the work follows. For each one there are the few sentences needed to frame it, the reference values already verified in our operational notes, the link to the note that goes deeper and the matching service page.
The figures quoted are standard and design references, taken from the operational notes published on this site: they are targets verifiable by measurement, not guarantees of outcome. The thresholds of an individual project are fixed on the real route, before the work starts.
Contents
- Design and optical budget
- Choosing the fibre: G.652 or G.657
- Installation: duct pulling and low-impact trenching
- Splicing: fusion or mechanical
- OTDR measurement: pulse, dead zones, launch cords
- Reading the test report
- As-built documentation and network records
- Specification compliance: the CPR classes
Stage 1 of 8
Design and optical budget
The optical budget is the maximum loss a link can absorb while staying within the equipment specification. It is calculated item by item before the cable is ordered — fibre attenuation, splices, connector pairs and, on PON networks, splitters — and compared with the optical class of the planned equipment. It is a binary threshold: if the sum of the losses exceeds it, the link does not respond.
The item that is almost always missing is the design margin: the decibel that will be needed in five years, after one repair and a few summers. A design handed over with zero residual margin is compliant on paper and fragile in real life.
Key values
- Single-mode G.652.D fibre: about 0.35 dB/km at 1310 nm and 0.25 dB/km at 1550 nm, read from the datasheet of the cable actually installed.
- Fusion splice 0.02-0.05 dB; clean UPC connector pair 0.2-0.3 dB, against the 0.75 dB allowed by ANSI/TIA-568.3-D.
- PON splitters from clause 6.6 of ITU-T G.671: 8.2-10.6 dB for a 1:8, 13.3-17.5 dB for a 1:32.
- Design margin of 2-3 dB for ageing, temperature and future repairs.
- Optical classes: GPON B+ 28 dB and C+ 32 dB (ITU-T G.984.2); XGS-PON N1 29 dB, N2 31 dB, E1 33 dB, E2 35 dB (ITU-T G.9807.1).
The service
ODN/PON design and optical budgetStage 2 of 8
Choosing the fibre: G.652 or G.657
The fibre is chosen on the bend radius the route actually imposes, not on a generic designation. G.652.D is the backbone fibre, historically characterised for wide radii, around 30 mm. Where the bend is unavoidable — dense patching, building entries, racks — the G.657 family is needed, and so is the subcategory, not the designation alone.
The difference is not theoretical: on the very same bend the macrobend loss changes by more than twenty times between one subcategory and another, and on an OTDR trace that loss looks like a poorly made splice.
Key values
- Minimum design radii: G.657.A1 10 mm, A2 and B2 7.5 mm, B3 5 mm; G.652.D historically characterised around 30 mm.
- Same 10 mm radius, one turn, at 1550 nm: A1 up to 0.75 dB, A2 up to 0.1 dB, B3 up to 0.03 dB.
- At 5 mm only B3 declares a limit: 0.15 dB at 1550 nm and 0.45 dB at 1625 nm.
- A1 and A2 are fully compliant with G.652.D; B2 and B3 only compatible, so not formally interchangeable on a mixed link.
The service
Support on tender specifications and complianceStage 3 of 8
Installation: duct pulling and low-impact trenching
A cable pulled beyond its limit almost never breaks on the spot: it answers later, with a few tenths of a dB that no test campaign can attribute to that day on site. Maximum pulling tension is a design figure and is calculated from the cable weight; the bend radius during installation is measured in cable diameters, not by eye. The duct is proved first: free of debris, not crushed, with the fill ratio checked together with the cables already in place.
On a public road the technique changes the site, not the permits. Low-impact trenching still requires the road-opening concession issued by the authority that owns the road, and the point where the job is won or lost is the road surface reinstatement, which has to be written in two phases.
Key values
- Nominal pulling load LS = 1.5 × the weight of 1 km of cable, capped at 2700 N (ITU-T L.100, clause 6.2.2.1).
- Long-term residual load LL equal to 30% of LS, with attenuation that must stay unchanged.
- Bending: 40 × the cable outer diameter while pulling, 20-30 × OD once installed.
- Air-assisted installation: pulling load an order of magnitude lower, typical pressure 10-12 bar, up to 3 km with a single machine (ITU-T L.156).
- Low-impact trenching: width from 3 to 20 cm, maximum depth 50 cm (Italian ministerial decree of 1 October 2013).
- Road reinstatement in two distinct phases, temporary and final, with responsibilities written into the specification.
Stage 4 of 8
Splicing: fusion or mechanical
Fusion and mechanical splicing are not two variants of the same technique. Fusion welds the two glasses and the link becomes a single fibre again; a mechanical splice aligns the two faces in a precision groove and entrusts optical continuity to a gel, which over the years gets contaminated, dries out and suffers thermal cycling — in a manhole or an outdoor cabinet more than anywhere else.
In a specification, “workmanlike execution” is not a requirement: it is a blank delegation. What is needed is the declared technique, the maximum loss per splice, the reflectance limit and the obligation to measure bidirectionally, otherwise someone else makes the choice for you.
Key values
- Fusion splice: 0.02-0.05 dB, normally non-reflective, below −60 dB.
- Mechanical splice: 0.1-0.3 dB, typical reflectance between −35 and −45 dB, with wider spread from one splice to the next.
- Sound threshold in a specification: bidirectional average ≤ 0.1 dB per splice, no splice above 0.15 dB, non-reflective splices.
- Mechanical splicing accepted for temporary restorations, with a scheduled and declared replacement.
The service
Optical-fibre splicingStage 5 of 8
OTDR measurement: pulse, dead zones, launch cords
Pulse width is the setting that weighs most on an OTDR measurement, and it is almost always the only one the specification never mentions. A long pulse carries energy to the far end of long links but merges close events into one; a short pulse separates events but leaves the trace in the noise. That is why a single acquisition is not a test campaign.
Launch and tail cords are not an accessory: without them the first and last connectors of the link stay inside the dead zone and never appear in the report. The cord is sized on the pulse actually used, not on habit.
Key values
- Pulse converted into metres of fibre: 10 ns ≈ 1 m, 100 ns ≈ 10 m, 1 µs ≈ 100 m, 10 µs ≈ 1 km.
- At least two acquisitions: a short pulse across the patching, a long pulse along the link.
- Launch and tail cords typically 1 to 2 km in outside plant (ITU-T G.650.3, clause 6.1.3); in a data room, 100-150 m cords with pulses of a few nanoseconds.
- Measurement in both directions and at at least two wavelengths: 1310 and 1550 nm on G.652 fibres.
- Group index set and declared: if it is wrong, the distances do not match the as-built records.
The service
OTDR certification and testingStage 6 of 8
Reading the test report
In a test report what is missing matters more than the values. Without the pulse width nobody knows what the instrument could see; without the cord lengths the first connector stayed invisible; without the second direction a splice can appear as an impossible gain. Tier 1 and tier 2 answer two different questions, and on the links that matter you need both.
Three questions are enough for whoever hands the document over: which direction did you measure in, with which thresholds, may I have the native files. If the answer to the last one is no, the first two are already answered.
Key values
- Tier 1: insertion loss of the whole link with a source and a power meter. Tier 2: event analysis with an OTDR.
- The value of an event is the bidirectional average: in the ITU-T G.650.3 example a splice reading 0.362 dB one way and −0.062 dB the other is worth 0.150 dB.
- Pass/fail thresholds from the specification, written together with the pulse they are measured with, not the instrument factory defaults.
- Native traces (.sor or equivalent) delivered alongside the PDF: without the measurement files nobody can re-verify anything.
- A match between the event table and the as-built records: every event on the trace must have a name on the diagram.
The service
OTDR certification and testingStage 7 of 8
As-built documentation and network records
The design says what was meant to be installed, the as-built says what is there: a diversion around an unexpected utility, a splice moved twenty metres, a cabinet rewired at the last minute. Without a point-by-point match between diagram and test traces a report stays an isolated PDF: it says the link worked on the day of measurement, and says nothing at all five years later.
Labelling is the part that gets paid for at the first emergency. It needs a unique code tying splices, drums and patch ports to their position on the diagram, because whoever intervenes in three years will not be whoever installed it.
Key values
- ISO/IEC 14763-2 treats documentation as part of the handover, not as an optional annex.
- Unique identification of spaces, cabinets, panels, cables and pathways following the TIA-606-C principle.
- Records: the Italian SINFI register was established by Legislative Decree 33/2016, implementing Directive 2014/61/EU; administrative fines for failing to report range from 5,000 to 50,000 euro.
- Updated at every network change: a five-year-old as-built is often worse than none.
Stage 8 of 8
Specification compliance: the CPR classes
Since 1 July 2017 “flame-retardant cable, compliant” identifies nothing: Regulation (EU) 305/2011 and the harmonised standard EN 50575 require CE marking and a Declaration of Performance, with seven reaction-to-fire classes and the subclasses for smoke, droplets and acidity. A class is written in full, and “halogen-free” is not a class.
The class is differentiated by intended use: risers, escape routes and crowded rooms do not carry the same requirements as secondary runs. At testing, compliance is demonstrated on the installed cable, checking by sampling that the designation printed on the sheath matches the specification and the Declaration of Performance.
Key values
- Seven classes from Aca to Fca; the designation written in full with smoke, droplets and acidity, for example Cca-s1b,d1,a1.
- Cca: THR1200s ≤ 30 MJ, FIGRA ≤ 300 W/s, flame spread ≤ 2 m. B2ca: THR1200s ≤ 15 MJ, FIGRA ≤ 150 W/s, FS ≤ 1.5 m.
- From B1ca to Dca the test is the vertical bundle test of EN 50399; for Eca the single-cable test of EN 60332-1-2 is enough.
- Surveillance: system 1+ with a notified body for classes Aca to Cca, system 3 for Dca and Eca, system 4 for Fca.
The service
Support on tender specifications and complianceThe thread that holds the eight stages together.
Every stage produces a number, and every number has to reappear in the next one: the attenuation estimated at design time reappears on the OTDR trace, the splice position on the trace reappears in the as-built records, the designation written into the specification reappears printed on the sheath of the installed cable. A network is certified when all those cross-checks exist and stay verifiable by someone who did not do the work.
The first step
A site survey. Then the numbers.
Tell us the environment and the need; we tell you times, methods and costs. Before we start, not after.
We reply within one business day. Survey and quote are free.